Aerospace coatings, most commonly thermal spray–based, are widely applied throughout the aerospace industry to enhance the performance and durability of typically metallic substrates. Because applied coatings are di cult to fully evaluate after deposition, it is critical that coating processes are well-defined and tightly controlled. Numerous process variables influence coating quality, and inadequate control can result in inconsistent properties, quality issues, reduced service life, and in-service part failures. As an additive process, poor control of coating applications can also lead to increased costs, excessive lead times, and program delays.
While industry standards exist, their interpretation and application can vary, and traditional customer audits or quality system standards such as AS9100 do not provide the level of detail needed to fully address critical coating processes. In response to these gaps, the Nadcap® Management Council approved the formation of the Coatings Task Group in 1995. Through the Nadcap® program, industry-developed audit criteria provide a consistent, in-depth approach to evaluating a wide range of coating technologies, helping ensure e ective process control across the aerospace supply chain.
View our "How to Get Started" page and walk through the necessary steps you'll need to take and get resources or create an EAN account to request a quote.

What are CT Industry Challenges?
- Calibration of Equipment – calibration provider not on Approved Supplier List, range of use, missing calibration tags, out of tolerance investigation, lack of flow down of requirements to calibration house, calibration master(s) not traceable to international standards
- Operator Qualification – no evidence or documentation of training/qualifications, or process of training/qualification
- Coatings evaluation not performed according to standards
- Coatings process parameters not clearly defined
- Coating application not consistent with expectations
- Preventative maintenance not identified / performed
- Contract Review not adequately performed

How a Nadcap CT Accreditation Supports You
- Working with peers to develop audit criteria and approve auditors used for the Nadcap accreditation program
- Coating and Lab technician qualification and training
- Participating in global coating supply chain assessment activities
- Customer attrition due to ability to satisfy requirements
- Improved on-time delivery
- Improved control of supply chain
- Mitigated in-service risk of failure
CT Nadcap Audit Criteria
AC7109 – Coatings Accreditation
AC7109/1 – Thermal Spray
AC7109/2 – Vapor Deposited Coatings
AC7109/3 – Diffusion Coating Processes
AC7109/4 – Stripping of Coated Material
AC7109/5 – Coating Evaluation
AC7109/6 – Plating of Coated Parts
AC7109/7 – Heat Treating for Supplier of Coatings
AC7109/8 – Grinding of Coatings as a Special ProcessThe PRI EANSM platform provides suppliers with a single place to view, understand, and navigate Nadcap Audit Criteria so you know exactly what will be assessed before, during, and after an audit. Create an EAN account to access the criteria and learn what you need to know to support your Nadcap accreditation.
Common Nonconformances Found During an CT Audit
- Content
The Auditee failed to follow internal procedure when preparing laboratory sample.
- Content
The Auditee failed to comply with internal procedure for maintaining grinding fluid concentration.
- Content
Auditor observed that parts were not fixtured according to internal procedure when loading furnace.
- Content
Process parameters for thermal spray process did not have defined tolerances.